Project Schedule

About

Project Schedule

We anticipate the following schedule for the North Metro Natural Gas Pipeline Project. Please note that the project schedule is subject to change

  • March 2016
    • Identified need for project
  • Spring 2016
    • Began preliminary route identification and engineering evaluation
  • August 2016
    • Began permitting process by conducting project overview meetings with Denver and Adams counties
  • October 2016
    • Hosted Adams County 1041 Permit Application open house
  • December 2016
    • Sent coordination letters to U.S. Fish and Wildlife Service and Colorado Parks and Wildlife
  • January 2017
    • Began route identification and collaboration with the City and County of Denver - elected officials, Public Works and Planning, North Denver Cornerstone Collaborative (NDCC)
    • Initiated Adams County 1041 Permit Application submittal
  • February 2017
    • Adams County 1041 Permit Application reviewed by referral agencies
  • April 2017
    • Submitted Site Development Plan and Zoning Permit Application to Denver
  • May 2017
    • Continued to collaborate with Denver on route identification
    • Attended Denver's Washington Street Corridor Study Open House
  • June 2017
    • Submitted final Adams County 1041 Permit Application
  • Summer 2017
    • Host open house in Denver
    • Attend Denver's Washington Sreet Corridor Study Open Houses
    • Submit permits to Denver Development Services and Public Works
    • Submit Public Works permits to Adams County
    • Submit Colorado Department of Transportation permit for highway crossings
    • Submit railroad crossing permits
  • Fall 2017
    • Begin preparations for construction at staging areas
    • Attend Denver's Washington Street Corridor Study Open House
    • Submit Street Cut permit to Denver
    • Submit air quality and stormwater permits to Colorado Department of Public Health and Environment
  • Winter 2017/2018
    • Continue to submit permits
  • Early 2018
    • Start construction in Denver and Adams counties
  • Spring 2018
    • Construction activities in Adams County along 62nd Street, Washington Street, 58th Avenue and Logan Court
  • Spring/Summer 2018
    • Construction activities in Denver along Washington Street between 45th and 50th avenues
  • Summer/Fall 2018
    • Construction activities along 45th Avenue between Washington Street and I-25
  • Spring/Summer/Fall 2019
    • Final construction activities and restoration of work areas along the entirety of the project
  • Late 2019
    • Complete project and put pipeline into service