Project Schedule

About

Project Schedule

We anticipate the following schedule for the North Metro Natural Gas Pipeline Project:

  • Spring 2016—Begin preliminary route identification and engineering evaluation
  • Summer 2016—Start project permitting process and conduct jurisdictional (Adams and Denver counties) project overview meetings
  • Fall 2016—Host required public open house in Adams County in support of 1041 Areas and Activities of State Interest Permit to provide project specific information
  • Winter 2017— Initial permitting submittals to jurisdictions and agencies
  • Summer 2017—Host City and County of Denver public open house to provide project specific information
  • Fall 2017—Project construction begins
  • Summer 2019—Testing, commissioning and bringing the pipeline into service
  • Fall 2019—Complete project construction, including restoration of sites

Please note that the project schedule is subject to change.